Quick answer: PPP models in India are contract structures that share funding, risk and operation of public assets between government and private developers. The main models are BOT (toll or annuity), BOOT, BOO, DBFOT, Hybrid Annuity Model (HAM) and TOT. The concession agreement fixes each party’s risks, and arbitration usually resolves disputes.
India builds highways, ports, airports and hospitals through public-private partnerships. The choice among PPP models in India decides who funds the project and who carries traffic and design risk. In January 2026, the Department of Economic Affairs (DEA) published a three-year pipeline of 852 PPP projects worth over ₹17 lakh crore. So developers, lenders and authorities will sign many new concessions soon.
What Are the Main PPP Models in India?
Each model differs in how much the private partner designs, finances, owns and operates:
- BOT (Toll): The developer finances and builds the asset, collects user charges and carries traffic risk, then hands the asset back.
- BOT (Annuity): The developer builds and maintains the asset, but the authority pays fixed annuities and keeps traffic risk.
- BOOT: The developer owns the asset during the concession and transfers ownership at the end.
- BOO: The developer builds, owns and runs the asset with no transfer back.
- DBFOT: The developer also takes design risk. India’s model BOT (Toll) highway concession follows this structure.
- Hybrid Annuity Model (HAM): The authority pays 40% of project cost in milestone tranches, and the developer arranges 60%.
- TOT: An operator pays an upfront sum to toll and maintain an existing road for a fixed period.
For highways, see our comparison of EPC vs BOT vs HAM.
How Government Supports PPP Projects
The Centre runs the Viability Gap Funding (VGF) scheme for projects that serve the public but cannot pay for themselves. After the 2020 revamp, most sectors can receive up to 40% of project cost. The Centre and the state each give up to 20%. Social sector projects, such as water supply and health, can receive up to 60%, and pilot health and education projects up to 80%.
In addition, the India Infrastructure Project Development Fund pays for feasibility studies and transaction advisers. The PPP Appraisal Committee (PPPAC) appraises central proposals, while an Empowered Committee clears VGF grants.
Risk Allocation and Common PPP Disputes
The concession agreement allocates risk clause by clause. Disputes usually arise over:
- delays in land handover and clearances;
- change of scope and cost overruns;
- traffic shortfall and toll revisions;
- termination and the termination payment formula;
- stamp duty on the concession itself.
Most model concessions route these disputes through conciliation and then arbitration.
Key Case Law on PPP Concessions
DMRC v. Delhi Airport Metro Express (SC, 10 April 2024): A three-judge bench allowed DMRC’s curative petition. It set aside an award of about ₹8,000 crore in a metro PPP dispute for perversity and patent illegality.
Rewa Tollway P. Ltd. v. State of Madhya Pradesh (2024 INSC 539): The Supreme Court held that a BOT concession granting toll rights is a lease under the Stamp Act. Such agreements can therefore attract lease stamp duty.
JDA v. Rohan Rajdeep Rajasthan Infra Project Ltd. (Rajasthan HC, 17 August 2026): A Division Bench set aside a ₹198.04 crore award on a Jaipur tunnel DBFOT project. The arbitrator had rewritten the design-risk allocation and awarded damages without finding a breach. The court also refused to treat the project’s 20.33% IRR as an interest rate.
Together, these rulings show that courts enforce the risk bargain as written. Our commercial litigation lawyers in Delhi NCR often see claims fail because parties skipped the contractual route.
FAQs on PPP Models in India
What are the PPP models in India?
The main models are BOT (toll and annuity), BOOT, BOO, DBFOT, HAM and TOT. They differ in who funds, owns and operates the asset.
What is the difference between BOT and BOOT?
Under BOT, the developer operates the asset but does not own it. Under BOOT, the developer owns it during the concession and then transfers it.
What is the hybrid annuity model?
The authority funds 40% of project cost during construction and repays the developer’s 60% through annuities. So the authority keeps traffic risk.
What is viability gap funding?
VGF is a government grant that makes a socially useful but commercially weak PPP project viable, usually up to 40% of project cost.
Who approves PPP projects in India?
The PPPAC appraises central PPP proposals, and an Empowered Committee under the DEA approves VGF support.
How are PPP disputes resolved?
Most concessions provide for conciliation followed by arbitration. Parties can challenge an award under Section 34 of the Arbitration and Conciliation Act, 1996.
Lex Pleaders advises contractors, employers, banks and NBFCs on PPP concessions, BOT, HAM and DBFOT projects, and concession disputes. Explore our infrastructure and construction law practice. As a law firm in Delhi NCR, we act before arbitral tribunals, High Courts and the Supreme Court. Write to us at lexpleadersindia@gmail.com to discuss your matter.
Disclaimer: This article offers general information only and does not constitute legal advice.