    There has been no advertisement, personal communication, solicitation, invitation or inducement of any sort whatsoever by or on behalf of Lex Pleaders India (OPC) Private Limited or any of its members to solicit any work through this website.
  2. Voluntary Access
    The user is accessing this website voluntarily and wishes to gain information about Lex Pleaders India (OPC) Private Limited for his/her/their own information and use.
  3. Information on User’s Request
    All information available on this website is provided solely at the user’s specific request, and any material accessed or downloaded is done entirely at the user’s own volition.
  4. No Lawyer–Client Relationship
    Accessing this website, submitting information, downloading material, or making any payment does not create a lawyer–client relationship between the user and Lex Pleaders India (OPC) Private Limited.
  5. Informational Purpose Only
    This website is intended for informational purposes only. While efforts are made to keep the information updated, no guarantee is given regarding completeness or accuracy.
  6. No Legal Advice
    The contents of this website do not constitute legal advice and should not be relied upon as a substitute for professional legal consultation.
  7. Limitation of Liability
    Lex Pleaders India (OPC) Private Limited disclaims all liability for any loss or damage arising from reliance on information provided on this website or on any external links.
  8. User Responsibility
    Any action taken by the user based on the information on this website is strictly at the user’s own risk.
  9. Intellectual Property
    All original content on this website (except statutory instruments and judicial precedents) is the intellectual property of Lex Pleaders India (OPC) Private Limited and may not be used without prior written consent.

By clicking “I AGREE”, that you have that read, understood, and accepted this disclaimer and the Terms & Conditions and Privacy Policy of the website.

Client signing construction contract.

Quick answer: Usually not. Section 6 of the RERA Act limits force majeure to war, flood, drought, fire, cyclone, earthquake or other natural calamities. The Haryana Real Estate Appellate Tribunal has repeatedly refused extra grace periods for NGT and pollution-control construction bans. So a GRAP stoppage rarely cancels a builder’s delay interest under Section 18.

On 6 November 2026, the air quality commission (CAQM) invoked GRAP Stage III across Delhi NCR and halted non-essential construction. Many builders will now cite a GRAP construction ban force majeure defence to push back possession dates. Homebuyers should know how RERA authorities actually treat that plea.

Is a GRAP Construction Ban Force Majeure Under RERA?

The RERA Act answers this in its own words. Section 6 lets the Authority extend a project’s registration for force majeure. Its Explanation then defines the term narrowly: war, flood, drought, fire, cyclone, earthquake or any other calamity caused by nature.

A GRAP order is neither war nor a natural calamity. Instead, it is a regulatory measure that recurs almost every winter. Homebuyers therefore argue that a prudent builder must plan for it. Meanwhile, Section 18 gives an allottee who stays in the project interest for every month of delay until possession.

However, most builder-buyer agreements carry wider force majeure clauses. These often list “orders of statutory authorities” or “NGT bans”. Builders rely on such wording, but tribunals read it against the statute, as the rulings below show.

Key Rulings on NGT and Pollution Bans as Force Majeure

Wonder City Buildcon v. Santosh Kumar Pandey (Haryana REAT, Appeal No. 242 of 2023, 8 December 2025): The promoter sought six more months for the second COVID wave, NGT bans and curbs on DG sets. The Tribunal called the plea misconceived. It held that the Section 6 definition controls and that a wider reading would unfairly favour promoters. It also noted that the Authority had already allowed the 12-month grace period in the agreement.

Signature Global v. Rampal Singh Chauhan (Haryana REAT, Appeal No. 346 of 2025, 26 August 2025): The Authority had already given a six-month COVID grace period. Consequently, the Tribunal refused any further force majeure concession and dismissed the builder’s appeals.

Newtech Promoters v. State of UP (Supreme Court, 2021): The Court described the allottee’s right to delay interest under Section 18 as unqualified. Courts still apply this principle when builders plead broad contractual clauses.

Runwal Constructions v. Bharat Shah (Bombay High Court, 8 June 2026, as reported): The Court reportedly held that a force majeure or waiver clause cannot defeat the statutory interest right.

The Exception: Government-Declared Force Majeure

Regulators can still grant blanket relief. For example, HRERA allowed a six-month COVID period from March to September 2020 in orders such as the Signature Global case. More recently, MoHUA advised State RERAs on 31 July 2026 to grant four months for the West Asia crisis. HRERA then extended eligible projects registered on or before that date. Notably, that relief rests on “war”, which Section 6 expressly covers. A pollution ban has no such anchor.

Delhi RERA and UP RERA apply the same central Section 6 definition. Even so, check each State’s circulars before you calculate your claim.

Checklist: What to Do If Your Builder Cites a GRAP Ban

  1. Find the due date. Read the possession clause and grace period in your builder-buyer agreement.
  2. Note the ban dates. Record when CAQM invoked and revoked each GRAP stage, and compare them with the builder’s claim.
  3. Test causation. Ask whether the project was already behind schedule before the ban began.
  4. Check registration. Look up the project page for any Section 6 extension order.
  5. Send a notice. Demand delay interest in writing and reject the force majeure claim.
  6. File a complaint. Approach the State RERA for interest or a refund. Experienced real estate dispute lawyers in Delhi NCR can frame the timeline evidence.

For the wider set of remedies, read our guide on what to do when a builder delays possession.

FAQs on GRAP Bans and RERA Delay Claims

Does GRAP Stage III count as force majeure for builders?

Generally, no. The Haryana Appellate Tribunal treats force majeure under RERA as limited to war and natural calamities, so pollution-related construction bans do not qualify.

Can a builder add GRAP ban days to the possession date?

Not automatically. The builder must prove the ban actually caused the delay. Even then, tribunals have refused extra time beyond the agreed grace period.

Is an NGT construction ban force majeure under RERA?

Haryana REAT rulings in 2025 called such pleas misconceived. NGT bans are regulatory orders, not calamities listed in Section 6.

Does a force majeure clause in the agreement override RERA?

No. Courts hold that a contract clause cannot defeat the statutory Section 18 right to delay interest.

Do I lose interest if RERA extends the project registration?

Not necessarily. A Section 6 extension concerns registration. Your interest claim depends on the agreed due date and the actual cause of delay.

Lex Pleaders advises homebuyers, investors, banks and NBFCs on RERA delay claims, force majeure disputes, refunds and builder litigation across Delhi NCR. As a law firm in Delhi NCR, we appear before RERA authorities and appellate tribunals. Write to us at lexpleadersindia@gmail.com to discuss your matter.

Disclaimer: This article offers general information only and does not constitute legal advice.