Quick answer: The NHAI conciliation process lets contractors and concessionaires settle highway disputes before a Conciliation Committee of Independent Experts (CCIE) under Part III of the Arbitration and Conciliation Act, 1996. Since January 2026, NHAI sends disputes of ₹10 crore or more to conciliation instead of arbitration. A signed settlement binds both parties like an arbitral award.
The NHAI conciliation process now decides how most large highway claims end. Contractors on EPC, HAM and BOT (Toll) projects once treated conciliation as a formality before arbitration. However, a 2026 policy shift changed that. For high-value claims, conciliation is now the main settlement route, with a civil suit as the fallback.
What Is the NHAI Conciliation Process?
NHAI set up Conciliation Committees of Independent Experts through Policy Circular No. 2.1.23/2017 dated 2 June 2017. Each committee has three members drawn from a panel of retired judges, civil servants, finance specialists and technical experts. The committee works under Part III of the 1996 Act, so Sections 61 to 81 govern its procedure.
Conciliation is voluntary: the committee helps parties agree but cannot impose terms. NHAI’s Executive Committee or Board must then approve any settlement, depending on its value.
How the ₹10 Crore Rule Changed NHAI Conciliation in 2026
On 12 January 2026, MoRTH directed a new value-based dispute clause. NHAI applied it on 19 January 2026 to BOT (Toll), HAM and EPC agreements. The key changes are:
- Parties first try amicable settlement for 30 days after a written dispute notice.
- Disputes below ₹10 crore go to institutional arbitration before SAROD or the India International Arbitration Centre.
- Disputes of ₹10 crore or more go to conciliation, not arbitration, and parties may still sue in civil courts.
- Declaratory and non-monetary disputes also stay out of arbitration.
- The new clause removes the Dispute Resolution Board (DRB) stage and applies to existing contracts, except arbitrations already underway.
NHAI’s Policy Circular No. 11.84/2026 of 13 February 2026 repeated this routing in its bidding documents. It also signals that mediation under the Mediation Act, 2023 will replace conciliation once notified.
Step-by-Step: Taking a Claim to Conciliation
- Serve a written dispute notice. Quantify each claim, because the ₹10 crore value decides the forum.
- Use the 30-day amicable window. Record every meeting and offer.
- Send a conciliation proposal. Under NHAI’s February 2025 SOP (Circular No. 2.1.80/2025), contractors paid a ₹5 lakh fee, while NHAI bore the committee’s costs.
- Attend the committee meetings. Support each claim with documents and calculations.
- Review the proposed terms. The committee formulates terms under Section 73, and you may comment before signing.
- Sign, or end the process. If talks fail, either party may terminate conciliation and file a civil suit or, for smaller claims, start arbitration.
Key Case Law on Conciliation and NHAI Disputes
Haresh Dayaram Thakur v. State of Maharashtra (SC, 5 May 2000): The Supreme Court held that a conciliator’s report binds nobody unless both parties sign a settlement agreement under Section 73. Therefore, nobody can enforce an unsigned proposal.
Mysore Cements Ltd v. Svedala Barmac Ltd (SC, 2003): The Court refused to treat a memorandum of conciliation and a letter of comfort as a Section 73 settlement. So, only a properly signed and authenticated agreement gains award status under Section 74.
Villupuram Highways Construction v. NHAI (Delhi HC, 29 July 2025): After failed CCIE conciliation, concessionaires sought court-appointed arbitrators. The court held that parties must nominate arbitrators from the SAROD panel. It found the panel broad-based, so the CORE (2024) ruling did not apply.
Practical Checklist for Contractors and Lenders
- List every NHAI contract and note whether its clause predates January 2026.
- Value each claim separately; do not bundle small claims to cross ₹10 crore by accident.
- Reserve your arbitration rights in writing if your original clause provides for it.
- Keep limitation in view, since conciliation does not stop the clock for a civil suit.
- Insist on a signed Section 73 agreement, not minutes or letters.
- Brief lenders early, because settlement terms can affect debt service.
Where conciliation fails, our commercial litigation lawyers in Delhi NCR can take the claim to the commercial court. You can also read more about our infrastructure and construction law practice.
Frequently Asked Questions
Is NHAI conciliation binding?
The process is not binding. However, a settlement agreement that both parties sign under Section 73 binds them and has the status of an arbitral award under Section 74.
Can a contractor go to arbitration for claims above ₹10 crore?
Under the 2026 clause, NHAI excludes these claims from arbitration. Contractors with older arbitration clauses may still argue that a circular cannot override a signed contract.
What happens if NHAI conciliation fails?
Either party can end the conciliation. The claimant can then file a civil or commercial suit, or arbitrate if the claim is below ₹10 crore.
Who sits on a Conciliation Committee of Independent Experts?
Three members from a notified panel of retired judges, senior civil servants, finance specialists and technical experts form each committee.
Does the 2026 rule apply to existing contracts?
NHAI applies it to existing BOT, HAM and EPC agreements, except arbitrations already underway. Contractors may challenge that retrospective effect.