⚠️ IMPORTANT LEGAL NOTICE

As per the rules of the Bar Council of India, lawyers and law firms are not permitted to solicit work or advertise.

By clicking “I AGREE”, the user expressly agrees and acknowledges that:

  1. No Solicitation or Advertisement
    There has been no advertisement, personal communication, solicitation, invitation or inducement of any sort whatsoever by or on behalf of Lex Pleaders India (OPC) Private Limited or any of its members to solicit any work through this website.
  2. Voluntary Access
    The user is accessing this website voluntarily and wishes to gain information about Lex Pleaders India (OPC) Private Limited for his/her/their own information and use.
  3. Information on User’s Request
    All information available on this website is provided solely at the user’s specific request, and any material accessed or downloaded is done entirely at the user’s own volition.
  4. No Lawyer–Client Relationship
    Accessing this website, submitting information, downloading material, or making any payment does not create a lawyer–client relationship between the user and Lex Pleaders India (OPC) Private Limited.
  5. Informational Purpose Only
    This website is intended for informational purposes only. While efforts are made to keep the information updated, no guarantee is given regarding completeness or accuracy.
  6. No Legal Advice
    The contents of this website do not constitute legal advice and should not be relied upon as a substitute for professional legal consultation.
  7. Limitation of Liability
    Lex Pleaders India (OPC) Private Limited disclaims all liability for any loss or damage arising from reliance on information provided on this website or on any external links.
  8. User Responsibility
    Any action taken by the user based on the information on this website is strictly at the user’s own risk.
  9. Intellectual Property
    All original content on this website (except statutory instruments and judicial precedents) is the intellectual property of Lex Pleaders India (OPC) Private Limited and may not be used without prior written consent.

By clicking “I AGREE”, that you have that read, understood, and accepted this disclaimer and the Terms & Conditions and Privacy Policy of the website.

Law Finance and Insolvency Solutions by Lex Pleaders Law Firm.

Quick answer: Excepted matters in construction contracts are disputes the contract keeps out of arbitration, usually by making an engineer’s or officer’s decision final. They remain valid. But after GVV Constructions v. Union of India (2026), the arbitral tribunal decides under Section 16 whether a claim is actually excepted, not the writ court.

Most government and PSU works contracts carry a wide arbitration clause. However, the same clause often carves out “excepted matters”. These carve-outs decide whether your claim reaches an arbitrator at all. This guide explains how excepted matters in construction contracts work, who decides them, and what contractors and employers should do.

What Are Excepted Matters in Construction Contracts?

The Arbitration and Conciliation Act, 1996 does not define the term. Typically, the contract names an authority, such as a Superintending Engineer or General Manager, and makes that person’s decision final.

Common examples include:

  • levy of compensation for delay by a named engineer;
  • rates for extra or substituted items under Railway GCC clauses;
  • reduced rates for sub-standard work;
  • “notified claims” gateways, where only listed claims may go to arbitration.

In Indian Railways contracts, Clause 63 of the General Conditions of Contract lists excepted matters. Clause 64, the arbitration clause, then excludes them.

Key Case Law on Excepted Matters

Mitra Guha Builders v. ONGC (SC, 8 November 2019). The Supreme Court held that a Superintending Engineer’s final decision on delay compensation was an excepted matter. Therefore, the arbitrator could not set it aside.

BSNL v. Motorola India (2009) 2 SCC 337. In contrast, the Court held that a clause that only quantified liquidated damages did not exclude the prior question of delay. As a result, the delay dispute stayed arbitrable.

Harsha Constructions v. Union of India (2014) 9 SCC 246. The Court ruled that referring an excepted dispute, or framing an issue on it, does not give the arbitrator jurisdiction.

Indian Oil Corporation v. NCC Ltd. (2023) 2 SCC 539. The Court upheld a notified-claims clause as a real limit on arbitral jurisdiction.

Office for Alternative Architecture v. IRCON Infrastructure (2025 SCC OnLine SC 1098). Once an arbitration agreement exists, the Section 11 court should not split claims into arbitrable and excepted parts. Instead, it should appoint the tribunal and leave the objection to it.

GVV Constructions v. Union of India (2026 INSC 976, decided 8 September 2026). A railway contractor challenged termination of its contract. The Supreme Court set aside a Telangana High Court order limiting the arbitrator’s remit. It held that the tribunal decides under Section 16 whether a claim falls within an excepted matters clause. The Court also noted that the exclusion keeps such matters out of arbitration, but does not stop a court from reviewing the authority’s decision.

Checklist: Handling an Excepted Matters Objection

  1. Read the clause closely. Check whether it names a decision-maker and expressly excludes the dispute from arbitration. A bare “not payable” clause is usually only a defence on merits.
  2. Separate liability from quantum. Following Motorola, argue that disputes on delay or fault remain arbitrable even if quantum is excepted.
  3. Use the contract machinery first. Contractors should approach the named authority and keep its decision on record.
  4. Raise the objection before the tribunal. Employers should raise it under Section 16, no later than the statement of defence.
  5. Avoid a premature writ. After GVV Constructions, a writ court is unlikely to fix the tribunal’s jurisdiction in advance.
  6. Keep the court route open. Where a matter is truly excepted, consider a civil suit against the authority’s decision, and track limitation.
  7. Preserve the Section 34 ground. If a tribunal decides a truly excepted matter, the losing party can challenge the award.

For a wider view of tiered clauses and appointments, see our guide to construction arbitration in India and our infrastructure and construction law practice. Where a dispute moves to a civil suit, our commercial litigation lawyers in Delhi NCR can assist.

FAQs on Excepted Matters

What are excepted matters in arbitration?

They are disputes the parties agreed to keep outside arbitration. Usually, a named officer’s decision on them is final and binding.

Who decides whether a claim is an excepted matter?

The arbitral tribunal decides it first under Section 16. The Supreme Court confirmed this in GVV Constructions (2026).

Can an arbitrator decide an excepted matter?

No. If a dispute is truly excepted, the arbitrator lacks jurisdiction, even if the parties referred it. A party can challenge such an award under Section 34.

Are liquidated damages an excepted matter?

It depends on the clause. In Mitra Guha, a final engineer’s levy was excepted. Under Motorola, however, the question of delay itself remained arbitrable.

Can a Section 11 court refuse to refer excepted claims?

Ordinarily, no. After Office for Alternative Architecture (2025), the court appoints the tribunal and leaves the objection to it.

What remedy does a contractor have for an excepted matter?

The contractor can approach a civil court against the authority’s decision. GVV Constructions confirms that courts may still examine such decisions.

Lex Pleaders advises contractors, employers, banks and NBFCs on excepted matters, arbitrability objections and construction claims. As a law firm in Delhi NCR, we act before arbitral tribunals, High Courts and the Supreme Court. Write to us at lexpleadersindia@gmail.com to discuss your matter.