By Lex Pleaders Editorial & Energy Regulatory Litigation Desk | Updated: November 22, 2026 | Reading Time: 8 mins
Key Legal Takeaways (Quick Reference)
– Statutory Restitution Principle: Change in Law clauses in competitively bid Power Purchase Agreements (PPAs) under Section 63 of the Electricity Act, 2003 are designed to restore the affected solar or wind developer to the same economic position as if the Change in Law had not occurred.
– Change in Law Rules, 2021: The Electricity (Timely Recovery of Costs due to Change in Law) Rules, 2021 prescribe a structured formula-based recovery mechanism and automatic pass-through timelines, reducing multi-year tariff uncertainty.
– Carrying Cost Entitlement: Consistent Supreme Court and APTEL jurisprudence affirms that where a PPA contains a restitutionary Change in Law clause, carrying cost is payable from the date the Change in Law event actually impacted the developer’s cash flows—not merely from the date of the regulatory order.
– Appellate Recourse: Adverse orders from CERC or State Commissions (such as TNERC, MERC, KERC, or DERC) are appealable before APTEL (New Delhi) within 45 days under Section 111 of the Electricity Act.
Why Change in Law & PPA Disputes Dominate Renewable Energy Litigation
India’s renewable energy expansion—especially across solar parks, hybrid projects, and wind corridors in Tamil Nadu, Rajasthan, Gujarat, Karnataka, and Maharashtra—relies heavily on long-term 25-year PPAs awarded through tariff-based competitive bidding under Section 63 of the Electricity Act, 2003. Because tariffs are locked for decades on razor-thin margins, subsequent statutory or fiscal changes—such as Basic Customs Duty (BCD) on solar modules, GST rate revisions, Safeguard Duty notifications, or grid-connectivity mandates—directly affect project bankability.
When procuring DISCOMs or intermediary procurers (SECI, NTPC, GUVNL, TANGEDCO) dispute eligibility, quantum, or carrying costs, developers must navigate a precise adjudicatory sequence before CERC (for composite interstate schemes under Section 79(1)(b)) or SERCs (for intrastate PPAs under Section 86(1)(f)), followed by appellate proceedings before APTEL.
What Qualifies as a “Change in Law” Event?
While exact eligibility depends on the specific PPA wording, Indian electricity jurisprudence recognizes the following core categories occurring after the bid cut-off date (typically 7 days prior to bid submission):
- Statutory Enactments & Amendments: Introduction of new taxes, duties, or cesses directly affecting the construction or generation cost of the power project (e.g., GST rollout, increase in GST on renewable energy devices from 5% to 12%, Safeguard Duty, and BCD notifications).
- Binding Notifications by Indian Governmental Instrumentalities: Statutory orders from the Ministry of Finance, Ministry of New and Renewable Energy (MNRE), or Central Electricity Authority (CEA) imposing mandatory technical or environmental compliance costs (e.g., Great Indian Bustard undergrounding compliance orders).
- Change in Interpretation of Law: Authoritative judicial or tribunal rulings altering the settled legal interpretation of a statutory levy applicable to power generation.
What Typically Does NOT Qualify
- Commercial price fluctuations in polysilicon, steel, or shipping freight unconnected to a statutory enactment.
- Internal corporate tax changes (unless expressly included in the PPA’s Change in Law clause).
- Costs incurred due to the developer’s own delay beyond the Scheduled Commissioning Date (SCOD), unless SCOD was validly extended by the procurer.
Forum Selection: CERC vs. SERC (e.g., TNERC) vs. APTEL
| Project & PPA Structure | Forum of First Instance | Statutory Provision | Appellate Forum |
|---|---|---|---|
| Inter-State / Composite Scheme (e.g., SECI/NTPC PPA supplying power to multiple states) | CERC (New Delhi) | Section 79(1)(b) & 79(1)(f), Electricity Act | APTEL (New Delhi) under Section 111 |
| Intra-State PPA (e.g., Tamil Nadu wind/solar PPA with TANGEDCO or State DISCOM) | Respective SERC (e.g., TNERC, KERC, MERC) | Section 86(1)(f), Electricity Act | APTEL (New Delhi) under Section 111 |
| Appeal Against CERC / SERC Order | APTEL (New Delhi) | Section 111(1) (45-day limitation) | Supreme Court of India under Section 125 |
Core Legal Issues Litigated in Solar & Wind PPA Disputes
1. Carrying Cost & Restitution
A recurring point of contention before CERC, SERCs, and APTEL is whether developers are entitled to carrying cost (interest on the incremental capital deployed to pay statutory duties/taxes prior to tariff recovery). Supreme Court rulings (including Uttar Haryana Bijli Vitran Nigam Ltd. v. Adani Power Ltd. and subsequent renewable energy precedents) have firmly established that restitution is incomplete without carrying cost when the PPA mandates restoring the party to the same economic position.
2. Notice Requirements & Cut-Off Dates
Most PPAs require the affected party to serve a Change in Law Notice to the procurer within a stipulated period upon becoming aware of the event. While APTEL has clarified in several cases that procedural notice clauses should not defeat substantive statutory rights where no prejudice is caused to the procurer, issuing a timely, itemized written notice with documentary backing remains critical to avoiding threshold objections.
3. Annuity vs. Lump-Sum Recovery & Reconciliation
Even after a Commission declares an event to be a valid Change in Law, disputes frequently arise over:
- Whether compensation must be paid as a lump sum or via annuity/monthly tariff adjustment over the remaining PPA term;
- The discount rate / carrying cost rate applicable to annuity schedules; and
- Verification of one-to-one invoice correlation (matching module import Bills of Entry, GST invoices, and CA certificates to the specific project).
4. Curtailment, “Must-Run” Status & Deemed Generation
In renewable-heavy states such as Tamil Nadu (TNERC), Andhra Pradesh, and Rajasthan, wind and solar developers also face backing-down instructions unrelated to genuine grid security. Under the Electricity (Promotion of Generation of Electricity from Must-Run Power Plant) Rules, 2021, renewable plants enjoy statutory “must-run” status; curtailment for commercial reasons (rather than grid safety) triggers compensation obligations under the PPA and applicable regulatory orders.
Pre-Filing Evidentiary Checklist for Renewable Developers
Before filing a Change in Law or PPA tariff petition before CERC/SERC—or challenging an adverse order before APTEL—legal and project finance teams should assemble:
- Executed PPA, RfS (Request for Selection), & Bid Submission Proof establishing the exact bid cut-off date.
- Statutory Notification Copies (Gazette notifications, Finance Ministry/CBIC circulars, MNRE/CEA directives).
- Chronological Change in Law Notices served on the DISCOM/procurer and all subsequent correspondence.
- Chartered Accountant (CA) Certified Cost-Impact Statement linking exact invoices, Bills of Entry, GST challans, and payment dates directly to the commissioned capacity.
- SCOD Extension Letters (where commissioning occurred after the original SCOD) proving that statutory levies were not caused by developer default.
Frequently Asked Questions (FAQs)
Can a solar or wind developer claim GST or Basic Customs Duty (BCD) increases under Change in Law?
Yes, provided the statutory notification increasing GST or imposing/modifying BCD was issued after the bid cut-off date specified in the PPA and the developer can substantiate the direct incremental cost impact with project-specific invoices and statutory filings.
What is the timeline to appeal an adverse TNERC, MERC, or CERC order before APTEL?
Under Section 111(2) of the Electricity Act, 2003, an appeal against an order of CERC or any State Electricity Regulatory Commission (such as TNERC) must be filed before APTEL in New Delhi within 45 days from the date of receipt of the order copy.
Are developers entitled to carrying cost on Change in Law claims?
Where the PPA includes a restitutionary Change in Law clause aimed at restoring the affected party to the same economic position, courts and APTEL have consistently upheld entitlement to carrying cost from the date the additional financial outlay was actually incurred until reimbursement.
Informational Resources & Related Legal Briefings
- Related Reading on Lex Pleaders:
- How to File a Section 111 Appeal Before APTEL: Timelines, Pre-Requisites, and Grounds Under the Electricity Act (
lexpleaders.com) - Upcoming Cluster Guide: Open Access, Wheeling Charges, and Cross-Subsidy Surcharges Before SERCs and APTEL
- Upcoming Cluster Guide: Commercial, Tax, and Regulatory Writ Litigation Before the Madras High Court
Power generators, renewable developers, and energy sector legal teams seeking procedural clarity on CERC, SERC, or APTEL litigation may explore our Energy & Electricity Regulatory practice overview or schedule an informational legal consultation at www.lexpleaders.com.
Disclaimer: This article is published strictly for general informational and educational purposes in compliance with Bar Council of India rules. It does not constitute legal advice, advertising, or solicitation, nor does reading or contacting Lex Pleaders create a lawyer-client relationship.