Quick answer: Risk and cost in construction contracts lets an employer terminate a defaulting contractor, award the balance work to another agency, and recover the extra cost from the original contractor. Recovery needs a valid termination for the contractor’s own default, a re-tender of the same scope, and proof of actual loss. Limitation usually runs from termination.
When a contractor abandons work or falls far behind, most government and PSU contracts let the employer finish the job “at the risk and cost” of the defaulter. Risk and cost in construction contracts is a strong remedy, but courts police it closely. This guide, part of our infrastructure and construction law work, explains how the clause works and what tribunals expect.
What Is Risk and Cost in Construction Contracts?
A risk and cost clause works in three steps. First, the employer terminates the contract for the contractor’s default. Next, it re-tenders the balance work to an alternative agency. Finally, it recovers the difference between the new price and the price it would have paid the original contractor.
CPWD-style Clause 3 provisions and many PSU general conditions follow this pattern. Employers usually adjust the excess against pending bills, security deposits or bank guarantees. They then raise any balance as a counter-claim in arbitration. For the wider termination process, see our guide on termination of construction contracts.
Four Conditions for a Valid Risk and Cost Claim
- Valid termination for the contractor’s default. If the employer caused the delay, the termination fails, and the claim fails with it.
- Proper notices. Most contracts demand show cause and cure notices before rescission.
- Same scope and specifications. The re-tender must cover the balance work, not a redesigned or upgraded project.
- Proof of actual excess. The employer must show the new contract value, the work done and the real loss.
Key Case Law on Risk and Cost Recovery
J.G. Engineers v. Union of India (SC, 2011). In this Guwahati airport dispute, the arbitrator found the employer responsible for the delay. The Supreme Court therefore held that the employer could neither levy liquidated damages nor recover the extra cost of completing the work through another agency.
Indian Oil Corporation v. SPS Engineering (SC, 2011). The Court accepted, as a general rule, that the claim crystallises once the employer awards the balance work at a higher price. However, a clause that measures loss by amounts actually spent may change that date.
Gillanders Arbuthnot v. SAIL (Delhi HC, Division Bench, 20 November 2024). The Bench restored an ICC award that held SAIL’s risk purchase claim of about ₹17 crore time-barred. It confirmed that re-tendering does not postpone limitation. The three-year period under Article 55 of the Limitation Act ran from termination.
Uppal Engineering v. IRCON (Delhi HC, 17 October 2025). The arbitrator had rejected IRCON’s ₹95 lakh risk and cost counter-claim. The new contractor took 15 months instead of five, for the same reasons the first contractor faced, so IRCON proved no real loss. Relying on that finding, Justice Sachin Datta also set aside the forfeiture of about ₹47 lakh in performance security.
Konarak Enterprise v. Haldia Development Authority (Calcutta HC, 25 September 2025). The tribunal had partly allowed the authority’s risk and cost counter-claim of about ₹18 lakh. A Division Bench of the Commercial Appellate Division later upheld recovery against the contractor, who had abandoned the project mid-way.
These disputes often run alongside bank guarantee and unpaid bill claims, which our commercial litigation lawyers in Delhi NCR handle in arbitration and before the High Court.
Checklist: Pressing or Defending a Risk and Cost Claim
- Read the termination clause, the notice periods and the risk and cost formula together.
- Build a delay record from the hindrance register, letters and site minutes to show who caused the delay.
- Check that each notice reached the right officer within the stated period.
- Compare the re-tender BOQ and specifications with the original balance work.
- Demand the new contract, measurement records and payment proof.
- Diary three years from termination and invoke arbitration well before that date.
FAQs
What does “at risk and cost” mean in a contract?
It means the employer may complete the remaining work through another agency and charge the defaulting contractor for any extra cost.
Can an employer recover risk and cost if the termination was illegal?
No. Under J.G. Engineers, if the employer caused the delay, it cannot recover the excess cost or liquidated damages.
Does the employer have to prove actual loss?
Yes. Tribunals reject claims where the new contractor faced the same hurdles and no real loss followed, as Uppal Engineering shows.
What is the limitation period for a risk and cost claim?
Usually three years under Article 55, counted from termination. Re-tendering does not extend it, unless the clause ties loss to amounts actually spent.
Can the employer change the scope in a risk and cost tender?
Generally not. If the re-tender upgrades or relaxes specifications, the employer risks losing the excess-cost claim.
Lex Pleaders advises contractors, employers, banks and NBFCs on termination, risk and cost recovery and construction arbitration claims. As a law firm in Delhi NCR, we act in arbitrations and before the Delhi High Court. Write to us at lexpleadersindia@gmail.com to discuss your matter.
Disclaimer: This article offers general information only and does not constitute legal advice.